Excavation & earthwork quantities

Earthwork Scenario Comparison

Compares two or three grading or excavation schemes drawn on the same site: cut by soil unit, compacted fill, reuse of the cut as fill, imported fill, loose export, truck loads, topsoil to stockpile and, with your own rates, the cost of each scheme and the change between two of them. The volumes come from the drawing and are never re-measured here.

Last updated
This page is provided by LogicCommons for informational purposes only. Results are analysis outputs computed from the inputs you supply and are not engineering advice, a design, or a substitute for review by a licensed professional under the codes adopted where the work is built. Verify all inputs and results independently.

LogicCommons is in beta. If a result, label, or reference looks wrong, tell us here; we read every message.

Methodology

Purpose and model boundary

This estimator compares two or three earthwork grading schemes drawn on one site: for example a building pad at two finished levels, a raised floor against a balance level, or one pad against two terraces. The canvas measures each scheme on the same soil model: the in-place (bank) volume of every soil layer its pads and excavations cut, the compacted fill its pads place above the existing ground, and the topsoil stripped under its fills. The calculation applies your swell and shrink factors, densities, soil uses, truck capacity and payload, and unit rates to each scheme, and reports the change between the two schemes you compare.

It is a quantity estimate for education and preliminary work. It does not design pads or slopes, check slope stability, excavation safety or bearing, or optimise a grading plan. The soil model is an interpretation between boreholes, not a survey of the ground.

Inputs and units

  • Units. Metres, one local coordinate system and one vertical datum. Volumes are cubic metres, masses tonnes, densities kilograms per cubic metre. Money is a plain number in your own currency.
  • Soil model. Borehole logs define the ground and the soil layers. Every scheme uses this one site, so a log edit applies to all of them. Each worked example loads sample site data (illustrative) with at least four boreholes.
  • Schemes. Two or three, each with its own name (1 to 32 characters). A scheme holds grading pads (an outline, a pad elevation, a cut slope and a fill slope as horizontal-to-vertical ratios, and whether the topsoil is stripped under the fill), fill pads (an outline, a top elevation and a side slope) and excavations (a flat bottom that reaches the ground, with a side slope). At most 31 objects per scheme.
  • Soil factors (one row per soil unit the schemes cut): swell factor (1.00 to 2.00), shrink factor (0.50 to 1.50) and an optional bank density (500 to 3,500 kg/m3).
  • Soil use (one row per soil unit): reuse as fill, export, or stockpile topsoil (at most one soil unit is the topsoil), with an optional disposal rate per loose cubic metre or per tonne.
  • Trucks: the truck capacity in loose cubic metres (1 to 60) and an optional payload in tonnes (1 to 100).
  • Schemes to show and compare: the scheme the detailed results show, and the first and second scheme of the comparison (Scenario 1, 2 or 3 is the first, second or third scheme on the canvas).
  • Unit rates (all optional, no default, 0 to 100,000, the same for every scheme): excavation per bank m3, haul per load, placement per placed m3, imported fill per placed m3 and topsoil per loose m3.

Governing relationships

For each cut row of a scheme, with bank volume B of a soil unit:

  • loose volume L = B x swell; placed volume P = B x shrink; mass M = B x density / 1000 when a density is given.
  • Reused soil placed P_R = the sum of P over the soil units used as fill; their loose volume L_R = the sum of L.
  • Imported fill = MAX(0, fill - P_R); surplus placed = MAX(0, P_R - fill).
  • Surplus loose = surplus placed x L_R / P_R (0 when there is no surplus). The surplus is exported.
  • Exported loose = the sum of L over the exported soil units + the surplus loose.
  • Topsoil loose = topsoil stripped x swell of the topsoil unit + any topsoil cut x the same swell.
  • Truck loads: export loads only, rounded up to whole loads per cut row, and limited by the payload where the soil has a density.

Calculation sequence

  1. The canvas measures every scheme on the shared site and checks that all of them use the same site model.
  2. The scheme rows are checked: each scheme's cut rows must add up to its drawing total, and its fill rows to its fill total.
  3. For each scheme: loose, placed and mass per soil unit; reuse, import and surplus; export, loads and topsoil.
  4. Each cost part is needed when its quantity is above zero, and priced when its rate is entered. A scheme's cost is Complete when every needed part is priced, Partial when some are, and Cost unavailable when none are.
  5. The two compared schemes give the changes (second minus first) and, when both are completely priced, the cheaper scheme.

Outputs and interpretation

  • Comparison: the two scheme names, the change in cut, fill, imported fill, export and loads, the change in total cost and the cheaper scheme. A positive change means the second scheme needs more.
  • Cost change by part: excavation, haul, disposal, placement, imported fill and topsoil. A part's change is blank when either scheme leaves it unpriced.
  • Scheme shown: its cut, fill, topsoil strip, reused soil, surplus, imported fill, export, loads, stockpiled topsoil, cost by part, total cost and cost status.
  • Tables: volumes, haul and cost of every scheme, and the cut of each soil unit in the two compared schemes.

Validation and status logic

The status line reads OK, CHECK with something to read with care, or NOT VALID with the first problem to fix. Under NOT VALID every result is blank. It is NOT VALID when the drawing was not measured, when the schemes were drawn on different site models, when a scheme's rows do not add up to its drawing total, when a soil unit with volume has no factors or use row, when more than one soil unit is set to stockpile topsoil, when topsoil is stripped but no soil unit is the topsoil, when a choice names a scheme that is not drawn, when the two compared schemes are the same, or when an input is outside its range. It reads CHECK when the compared schemes are not both completely priced, so no cheaper scheme is named, and when the ground model uses the approximate Natural Neighbor method.

Assumptions and limitations

  • Every scheme is measured on the same interpolated soil model, so the comparison is fair, but the model itself is only as good as the boreholes.
  • A grading pad cuts where the ground is above its elevation and fills where it is below, with straight slopes up or down to the ground. Fill counts only what lies above the existing ground; overlapping pads and cuts are counted once.
  • Topsoil can be stripped only where the top soil layer is the topsoil, under the fill of a pad.
  • Swell, shrink and density factors are estimates; real values vary by about one third.
  • No haul distance, equipment, schedule or compaction specification is modelled.

Restrictions and non-computing states

  • Calculate stays off until two or three schemes are drawn and every one can be measured on the site.
  • Until an update to the drawing library lands, the pads' volumes cannot be measured; the canvas says so and Calculate stays off. The pads can still be drawn and edited.
  • A drawing longer than 30,000 characters is not stored as text with the result; it is traced by its snapshot id.

Errors and warnings

  • An object over ground the soil model does not cover is refused; move it inside the borehole area.
  • A pad slope that cannot reach the ground, or an outline that crosses itself, is refused and the object stays as it was.
  • A scheme with nothing drawn, or a third scheme beyond the limit, keeps Calculate off.
  • Read a Partial or Cost unavailable cost status with the blank cost parts it names before comparing totals.

References

Sources and further reading

  • Earthwork estimating factors (loose swell, embankment swell or shrinkage, and in-place densities by material): U.S. Federal Highway Administration, Office of Federal Lands Highway, Project Development and Design Manual, Chapter 9 Highway Design, "Earthwork Design", Exhibit 5.1 A (page last updated 15 January 2026). The exhibit says its factors vary by about one third and are for estimating before project data exist. highways.fhwa.dot.gov
  • Earthwork computations, shrink and swell, balancing and topsoil replacement: Montana Department of Transportation, Road Design Manual, January 2026, sections 13.3.1 to 13.3.5 and 13.6.3. mdt.mt.gov
  • The excavation rate in the worked examples (USD 24.00 per cubic metre, unclassified excavation, item 203100000): Montana Department of Transportation, Weighted Average Prices Catalog, 1 January to 31 December 2025. mdt.mt.gov

The haul, placement, imported fill, topsoil and disposal rates, the truck capacities and the payload in the examples are illustrative assumptions dated 2026-11-20. Replace every factor and rate with your project's own values. Pad and slope design, slope stability and excavation safety are outside this estimator and are not assessed here.