Purpose and model boundary
This estimator turns the excavations you draw into the soil they remove, layer by layer, and then into loose and placed volumes, masses, truck loads and costs for up to three disposal scenarios. The canvas measures the in-place (bank) volume of every soil unit each excavation stage removes. The calculation applies your swell and shrink factors, densities, truck capacity and payload, destinations and unit rates.
It is a quantity estimate for education and preliminary work. It does not check slope stability, design shoring or dewatering, classify soil for disposal, or judge whether a cut can be dug as drawn. The soil model is an interpretation between boreholes, not a survey of the ground.
Inputs and units
- Units. Metres, one local coordinate system and one vertical datum. Volumes are cubic metres, masses tonnes, densities kilograms per cubic metre. Money is a plain number in your own currency.
- Soil model. Borehole logs (collar position and elevation, and the depth of each layer) define the ground surface and the contacts between layers. Each worked example loads sample site data (illustrative) with at least four boreholes. You edit the logs in the Borehole observations card, or import borehole data.
- Excavations. Up to 31 cuts, each a rectangle or a polygon floor at a flat bottom elevation, with sides that are vertical or sloped at a horizontal-to-vertical ratio, reaching up to the existing terrain.
- Stages. Each excavation belongs to exactly one stage, and the stages are dug in order. At most 8 stages.
- Soil factors (one row per soil unit that has volume): swell factor (1.00 to 2.00), shrink factor (0.50 to 1.50) and, optionally, the in-place density (500 to 3,500 kg/m³).
- Destinations: for each soil unit and scenario, EXPORT, REUSE or STOCKPILE. Scenario 1 is required; scenarios 2 and 3 are optional, and the shown scenario selects which one the totals report.
- Haul and disposal: truck capacity in loose cubic metres (1 to 60), optional payload in tonnes, the disposal rate basis (per loose m3 or per tonne) and an optional disposal rate per soil unit; whether the excavation is refilled.
- Unit rates (all optional, no default): excavation per bank m³, haul per load, placement per placed m³, stockpile per loose m³ and imported fill per placed m³.
Governing relationships
For each row of the snapshot (one stage and soil unit, bank volume B of soil unit m):
- Loose volume L = B × swell(m). Placed volume P = B × shrink(m). Mass M = B × density(m) / 1000 tonnes, when the density is given.
- Truck loads for an exported row = the larger of L / capacity and, when a payload and a density are given, M / payload, rounded up to a whole load.
- Disposal quantity = L (per loose m3) or M (per tonne, only with a density); disposal cost = quantity × rate.
- Fill required = the total bank volume when the excavation is refilled, else 0. Imported fill = the fill required less the reused placed volume, never below 0; a reuse surplus is reported when the reused volume exceeds the fill.
- Each cost part is its quantity times its rate: excavation (total bank), haul (loads), disposal (exported rows), placement (reused placed volume), stockpile (stockpiled loose volume) and imported fill.
Calculation sequence
- The canvas builds the soil surfaces from the borehole logs (piecewise planar between boreholes, or Natural Neighbor sampled onto a fine mesh when you choose it).
- For each stage k it measures the union of the cuts of stages 1 to k, by soil unit, so overlapping cuts count once. The stage's own volume is that union less the union of the stages before it.
- The page sends those rows, their total and the snapshot header to the calculation, with your inputs.
- The calculation checks the snapshot and the inputs, then applies the relationships above for each scenario in use.
Outputs and interpretation
Results report the shown scenario's bank, loose and placed volumes, masses, loads and the six cost parts, the total cost and its status, and a comparison of the three scenarios. The tables give the volumes, haul and cost by soil unit and the bank volume, loads and cost by stage. A missing rate is never a zero cost: a needed part without a rate is left blank and the cost status is PARTIAL, or COST_UNAVAILABLE when no needed part is priced.
Worked examples
Selecting an example replaces the current project. Save your edits first. The factors and rates in the examples are illustrative and must be replaced with your own.
- Business-park building-pad excavation. A 60 × 40 m pad floor at 115.5 m with 1H:1V sides, one stage. Topsoil is stockpiled and silty sand reused; one rate is left blank, so the cost is PARTIAL.
- Basement excavation by soil class. A 24 × 18 m vertical-sided basement 6 m deep. Densities are entered, disposal is priced per tonne and the loads are limited by the payload.
- Soft-clay pocket remove and replace. An octagonal floor over the thick core of a soft-clay pocket at 107.5 m with 1H:1V sides, compared in two scenarios with the excavation refilled. A flat floor cannot follow the pocket's base, so some stiff clay below the thinner pocket edge is also removed, and the thin margin outside the cut stays.
- Highway cut in two stages. A 400 m cut: stage 1 to 113.7 m at 1.5H:1V, stage 2 inside it to 109.7 m at 1H:1V. Each stage's rows count only the soil the earlier stage left.
- Warehouse pad cut to formation. A 120 × 60 m pad cut to a flat formation at 101.8 m. The topsoil strip and sub-cut of the brief are shown as one cut, because an excavation floor is flat; the depth varies with the ground. No rates are entered, so the cost is unavailable.
Validation and status logic
The status reads OK, CHECK: (a valid result with a caution) or NOT VALID: (no result). The first rule that applies wins: the snapshot status (a drawing changed after it was measured, or one the canvas could not measure, is refused), then the snapshot rows (each needs a stage, a soil unit and a volume from 0 to 10,000,000 m³, and the rows must add up to the drawing's union total), then the soil factors, destinations and disposal rates (each soil unit with volume needs a factors row and a scenario 1 destination), then the truck, refill and rate inputs. A Natural Neighbor model gives CHECK: volumes are approximate.
Assumptions and limitations
- Volumes are bank (in-place) volumes of the interpreted soil model; the model is only as good as the logs and the correlation between them, and nothing is extrapolated outside the boreholes.
- Excavation floors are flat; sloped sides offset each edge outward by the slope times the height.
- Swell, shrink and density factors vary widely with the material and its moisture; published estimating factors are for planning before project data exist.
- Stage costs exclude imported fill; haul is counted in whole loads per soil unit row.
Restrictions and non-computing states
The canvas refuses a cut outside the logged ground, below the deepest log, or across an excluded area, and then sends no rows, so Calculate stays blocked until the cut or the soil model is fixed. More than 31 cuts, 8 stages or 12 soil units with volume are not supported.
Errors and warnings
Every refusal names the first problem: the field, the row or the snapshot check that failed, in plain words, with the allowed range. The canvas status line names a cut it cannot measure in GeoCanvas's own words.
References
Sources and further reading
- Earthwork estimating factors (loose swell, embankment swell or shrinkage, and in-place densities by material): U.S. Federal Highway Administration, Office of Federal Lands Highway, Project Development and Design Manual, Chapter 9 Highway Design, "Earthwork Design", Exhibit 5.1 A (page last updated 15 January 2026). The exhibit says its factors vary by about one third and are for estimating before project data exist. highways.fhwa.dot.gov
- Unit price for unclassified excavation used in the illustrative examples: Montana Department of Transportation, Weighted Average Prices Catalog, 1 January to 31 December 2025 (dated 2 January 2026), item 203100000 Excavation-Unclassified.
The other example rates, the truck capacity and the payload are illustrative assumptions of the examples, dated 2026-11-19. Replace every factor and rate with your project's own values. Soil classification for disposal, slope stability and excavation safety are outside this estimator and are not assessed here.