Excavation & earthwork quantities

Soil Stockpile Volume

Turns the stockpile volumes measured in the drawing into bank and placed volumes, mass, the area a respread pile covers, truck loads and, with your own rates, the cost of loading, hauling, disposal, cover and sediment barrier, plus the value of the material kept in stock. The volumes come from the drawing and are never re-measured here.

Last updated
This page is provided by LogicCommons for informational purposes only. Results are analysis outputs computed from the inputs you supply and are not engineering advice, a design, or a substitute for review by a licensed professional under the codes adopted where the work is built. Verify all inputs and results independently.

LogicCommons is in beta. If a result, label, or reference looks wrong, tell us here; we read every message.

Methodology

Purpose and model boundary

This estimator measures soil stockpiles drawn on a site and turns their loose volume into bank and placed volumes, masses, the area a topsoil pile can respread, truck loads, erosion-control quantities and costs. The canvas measures each pile on the existing ground of the site's soil model: its loose (as piled) volume, toe area, toe perimeter, cover area and, when the site has an excavation, the distance from its toe to the excavation edge. The calculation applies your swell and shrink factors, densities, truck capacity and payload, and unit rates.

It is a quantity estimate for education and preliminary work. It does not check slope stability or excavation safety, classify soil, or judge whether a pile can be built as drawn. The soil model is an interpretation between boreholes, not a survey of the ground.

Inputs and units

  • Units. Metres, one local coordinate system and one vertical datum. Volumes are cubic metres, areas square metres, masses tonnes, densities kilograms per cubic metre. Money is a plain number in your own currency.
  • Soil model. Borehole logs define the ground surface the piles sit on. Each worked example loads sample site data (illustrative) with at least four boreholes. You edit the logs in the Borehole observations card, or import borehole data.
  • Piles. Up to 32 piles, each a windrow or rectangular crest (centre, length along its axis, width, rotation), a cone apex, a crest outline, or a surveyed pile (survey shots of its top and its toe line). Each has a crest elevation, a side slope as a horizontal-to-vertical ratio and a material name.
  • Materials (one row per material a pile is made of): swell factor (1.00 to 2.00), shrink factor (0.50 to 1.50) and its use: respread on site, reuse as fill, export, or keep in stock. An optional density table gives each material's bank density (500 to 3,500 kg/m3).
  • Respread and haul: the loose respread depth (0.025 to 1 m, optional), the truck capacity in loose cubic metres (1 to 60; needed only when a pile is exported or reused as fill) and an optional payload in tonnes (1 to 100).
  • Unit rates (all optional, no default, 0 to 100,000): loading per loose m3, haul per load, disposal per loose m3, cover per m2, sediment barrier per m and material value per tonne.

Governing relationships

For each pile with loose volume L of material m:

  • Bank volume B = L / swell(m). Placed volume P = B × shrink(m). Mass M = B × density(m) / 1000 tonnes, when the density is given.
  • Truck loads for a pile that is exported or reused as fill = the larger of L / capacity and, when a payload and a density are given, M / payload, rounded up to a whole load.
  • Overlapping piles of one material: the shared volume is counted once. As an accounting split (not a geometric one), it is shared among that material's piles in proportion to their own volumes: a pile's counted loose volume = its own volume × (the material's volume with overlaps counted once / the sum of its piles' own volumes). Piles of different materials may not overlap.
  • Respread area = the sum over the respread piles of L / respread depth.
  • Each cost part is its quantity times its rate: loading (loose volume, every pile not kept in stock), haul (loads), disposal (exported loose volume), cover (cover area) and sediment barrier (toe perimeter). The material value (mass × rate per tonne) is reported on its own and is not part of the total cost.

Calculation sequence

  1. The canvas builds the ground surface from the borehole logs (piecewise planar between boreholes, or Natural Neighbor sampled onto a fine mesh when you choose it).
  2. For each pile it builds the pile surface: the crest at its elevation, with sides sloping down at the side slope until they meet the ground. The pile volume is the volume between that surface and the ground where the pile is above the ground; ground below the original surface is not pile.
  3. It measures each pile, the total of all piles and the total of each material's piles, with overlapping piles counted once.
  4. The page sends those rows, their total and the measurement header to the calculation, with your inputs.
  5. The calculation checks the measurement and the inputs, then applies the relationships above.

Outputs and interpretation

Results report the number of piles, the loose total (overlaps counted once), the piles added up and the overlap, the bank and placed totals, the mass, the respread area, the exported volume and truck loads, the toe area, the sediment-barrier length, the cover area, the five cost parts, the total cost and its status, and the material value. The tables give the totals by material, and per pile its volumes as drawn, its use, mass and loads, and its cost. A missing rate is never a zero cost: a needed part without a rate is left blank and the cost status reads "Partial: some needed rates are blank", or "Cost unavailable: no needed rates entered".

Worked examples

Selecting an example replaces the current project. Save your edits first. The sites, factors and rates in the examples are illustrative and must be replaced with your own.

  1. Business-park topsoil windrows. Three windrows, crest 40 × 2 m, 3 m high with 1.5H:1V sides, in two rows on the sloping north strip of a business park (end to end they would not fit on the site); respread at a 4 in (0.1016 m) loose depth.
  2. Highway topsoil salvage piles. Four windrows, crest 60 × 3 m, 2.5 m high with 2H:1V sides, along the south edge of a 600 m highway corridor, kept in stock, with cover and sediment-barrier rates.
  3. Basement spoil pile beside the cut. One sand pile with a 10 × 6 m toe, 2.5 m high with 1H:1V sides, its toe 0.4 m from the top edge of the basement cut, exported in payload-limited trucks. The cut is drawn 24 × 12 m, smaller than a 24 × 18 m basement, so that the pile fits beside it on this small site.
  4. Month-end survey of an imported fill pile. A gravel fill pile measured from survey shots of its top and its toe line, kept in stock and valued per tonne.
  5. Six subdivision piles, two overlapping, no prices. Three topsoil windrows, two stiff-clay cones whose toes overlap (the shared soil is counted once) and one sand pile, all kept in stock; no rates, so the cost is unavailable.

Validation and status logic

The status reads OK, CHECK: (a valid result with a caution) or NOT VALID: (no result). The first rule that applies wins: the measurement status (a drawing changed after it was measured, or one the canvas could not measure, is refused), then the pile rows (each needs a name, a material from the Materials table and a volume from 0 to 1,000,000 m3, and the rows must agree with the drawing's total), then the materials and densities, then the respread depth, truck and rate inputs. A Natural Neighbor ground model gives CHECK: volumes are approximate. A pile toe closer than 0.61 m (2 ft) to an excavation edge gives a CHECK that states the distance and quotes the rule that spoil be kept at least 0.61 m (2 ft) from the edge; this estimator does not check excavation safety. Overlapping piles of one material give a CHECK naming the overlap; the toe, perimeter and cover areas are the piles' own and are not reduced by it.

Assumptions and limitations

  • Pile volumes are loose (as piled) volumes on the interpreted ground; the ground is only as good as the logs, and nothing is extrapolated outside the boreholes.
  • Pile sides are planes at one slope from the crest down to the ground; a real pile's faces are not exactly planar.
  • Cones are measured as 64-sided shapes, about 0.16 % below a true cone on level ground.
  • Swell, shrink and density factors vary widely with the material and its moisture; published estimating factors are for planning before project data exist.

Restrictions and non-computing states

The canvas refuses a pile whose toe reaches ground the soil model does not cover, and then sends no rows, so Calculate stays blocked until the pile or the soil model is fixed. More than 32 piles are not supported. While the drawing's pile measurement waits for an update, the page says so and Calculate stays off.

Errors and warnings

Every refusal names the first problem in plain words: the pile, the field or the measurement check that failed, with the allowed range. The canvas status line names a pile it cannot measure.

References

Sources and further reading

  • Earthwork estimating factors (loose swell, embankment swell or shrinkage, and in-place densities by material): U.S. Federal Highway Administration, Office of Federal Lands Highway, Project Development and Design Manual, Chapter 9 Highway Design, "Earthwork Design", Exhibit 5.1 A (page last updated 15 January 2026). The exhibit says its factors vary by about one third and are for estimating before project data exist. highways.fhwa.dot.gov
  • Topsoil salvage, stockpiling and the 4 in loose respread depth used in the examples: Montana Department of Transportation, Road Design Manual, January 2026, section 13.6.3 Topsoil. mdt.mt.gov
  • Stockpile erosion controls (a sediment barrier along the downgradient perimeter, and cover or stabilisation for piles left unused): U.S. Environmental Protection Agency, 2022 Construction General Permit, as modified April 2025, Part 2.2.5. epa.gov
  • Keeping excavated material at least 2 ft (0.61 m) from the edge of an excavation, or retaining it: U.S. Occupational Safety and Health Administration, 29 CFR 1926.651(j)(2). osha.gov

The truck capacity and payload, the cover, sediment-barrier and material rates in the examples are illustrative assumptions dated 2026-11-20. Replace every factor and rate with your project's own values. Slope stability, excavation safety and soil classification are outside this estimator and are not assessed here.

Results are informational and not professional advice. See our Terms of Use. Powered by SpreadsheetWeb · About · Privacy · Terms